1. Before measurement, screw the test leads onto the two binding posts respectively, and adjust the meter pointer to the zero scale line.
2. Place the test leads connected to the binding posts on the two points to be measured (e.g., rails, water pipes, cable sheaths, coal, ground, etc.). The two test points should be on different conductors, with a distance of about 2 meters. Normally, measure every 50-100 meters, or determine test points temporarily as needed. Set the switch to an appropriate range, and the meter reading, after conversion, will give the corresponding current value.
3. During measurement, ensure good contact between the hard alloy tip of the measuring probe and the object under test. The instrument should be placed horizontally to ensure accurate readings.
4. When no AC stray current is detected at a location, also test for DC stray current, and vice versa.
5. When measuring stray voltage, the ranges correspond as follows: 50mA corresponds to 0.2V, 250mA to 1V, 1A to 4V, 5A to 20V, and 10A to 40V. (That is, the current value multiplied by 4 gives the voltage value.)
6. When the magnitude of stray current is unknown, first set to the maximum range, then gradually decrease until an appropriate measuring range is reached.
7. When the measured current exceeds 5A, the instrument should only be used for short-term measurements. When the measured current exceeds 10A, the instrument should only be used for instantaneous measurements to avoid burning out components and the meter.
8. When measuring DC stray current, if the meter pointer deflects in the reverse direction, swap the test leads.